- 14:3314:33, 6 May 2024 diff hist +232 CEGS Creation →Cleanup HACS Host Computer / Laptop: added step for valve positioning
- 14:2614:26, 6 May 2024 diff hist −4 m CEGS Creation →CEGS Packing and Shipping: formatting
- 14:2314:23, 6 May 2024 diff hist +1 m CEGS Creation →Wrapping
- 14:2214:22, 6 May 2024 diff hist +188 m CEGS Creation →Wrapping
- 14:2014:20, 6 May 2024 diff hist +1 m CEGS Creation →Removal Procedure: formatting
- 14:1814:18, 6 May 2024 diff hist −3 m CEGS Creation →Loose Item Removal
- 14:1514:15, 6 May 2024 diff hist +4,497 CEGS Creation Added a section for packing and shipping the CEGS itself
- 13:5613:56, 6 May 2024 diff hist +5 m CEGS Creation Moved some titles around
- 13:5313:53, 6 May 2024 diff hist +9,658 CEGS Creation Added a section to the packing procedure detailing the loose item removal and wrapping/packing
- 12:4912:49, 6 May 2024 diff hist +216 m CEGS Creation No edit summary
25 April 2024
- 19:3819:38, 25 April 2024 diff hist −40 CEGS Creation Removed the 'Exercise all LN valves' part of the LN Manifold section, since it is an obsolete step
- 19:3519:35, 25 April 2024 diff hist +396 CEGS Creation Added new procedure for LN valve flow rates, and edited the LN closed valve position to be +820 rather than +1000 from open position.
22 April 2024
- 17:2617:26, 22 April 2024 diff hist −28 m CEGS Creation Edited thermistor calibration numbers slightly
16 April 2024
- 18:0818:08, 16 April 2024 diff hist +143 m CEGS Creation Added some small items to inspection Tag: Visual edit: Switched
- 18:0318:03, 16 April 2024 diff hist +974 N Grounding Kit Creation Created page current
9 April 2024
- 17:1117:11, 9 April 2024 diff hist +206 CEGS Creation Modified the GasSupplies Integration step to indicate the use of the Test() function rather than manually testing
- 16:2716:27, 9 April 2024 diff hist +355 m CEGS Creation Added a few small things to the GasSupplies section
- 14:4914:49, 9 April 2024 diff hist +154 m CEGS Creation Modified the flow valve procedure slightly Tag: Visual edit: Switched
- 13:1913:19, 9 April 2024 diff hist +95 m CEGS Creation No edit summary
- 13:1713:17, 9 April 2024 diff hist +855 CEGS Creation Added procedure for adjusting the gas cylinder regulators
5 April 2024
- 12:4112:41, 5 April 2024 diff hist +71 CEGS Creation Moved the air pressure regulator installation instructions to after the air lines have been installed.
2 April 2024
- 12:4112:41, 2 April 2024 diff hist +18 m CEGS Creation No edit summary
- 12:2912:29, 2 April 2024 diff hist +327 CEGS Creation Added instructions for UPS battery setup in case the yellow sticker is missing
1 April 2024
- 20:3720:37, 1 April 2024 diff hist +147 CEGS Creation Added a step to USB power settings section
- 20:3520:35, 1 April 2024 diff hist +193 CEGS Creation Added the steps to hook up the UPS battery to first time power, and modified the USB Power Management section to be up to date
- 20:1020:10, 1 April 2024 diff hist 0 m CEGS Creation Fixed an error in the first time power section, where the PBD bus probe value was incorrectly set to 5.5 +/- 0.5 rather than 5.0 +/- 0.5.
29 March 2024
- 18:0118:01, 29 March 2024 diff hist −144 m PS Terminal Guard Creation No edit summary current
- 18:0118:01, 29 March 2024 diff hist +831 N PS Terminal Guard Creation Created page
- 15:4915:49, 29 March 2024 diff hist 0 m CEGS Creation Fixed formatting errors
27 March 2024
- 20:3120:31, 27 March 2024 diff hist +1,454 CEGS Creation Added an Inspection section before integration to check that the system is mechanically ready for integration, edited the furnace integration sections, and edited the VTC warm operation steps
25 March 2024
- 16:3816:38, 25 March 2024 diff hist +73 CEGS Creation Added a diagram for the meter calibration section Tag: Visual edit
- 16:3516:35, 25 March 2024 diff hist +104 N File:U6IFC Dividers.png No edit summary current
13 February 2024
- 13:0413:04, 13 February 2024 diff hist +2,317 LN Tank Scale Creation No edit summary current Tag: Visual edit: Switched
1 February 2024
- 16:5516:55, 1 February 2024 diff hist +60 N File:LN Scale Before Attaching Top.jpg No edit summary current
- 16:5316:53, 1 February 2024 diff hist +58 N File:LN scale tape and rubber seal configuration.jpg No edit summary current
- 16:4916:49, 1 February 2024 diff hist +90 LN Scale Electronics Creation Added wiring diagram current Tag: Visual edit
- 16:4916:49, 1 February 2024 diff hist +75 N File:LN Scale Electronics Wiring Diagram.png No edit summary current
- 16:4716:47, 1 February 2024 diff hist +1,015 LN Tank Scale Creation No edit summary Tag: Visual edit
- 13:4913:49, 1 February 2024 diff hist +1 m LN Tank Scale Creation Finished article Tag: Visual edit
- 13:2613:26, 1 February 2024 diff hist +85 N File:LN Scale Wiring Diagram2.png No edit summary current
31 January 2024
- 19:3919:39, 31 January 2024 diff hist +33 N File:LN Scale Wiring Diagram.png No edit summary current