Heater Controller Stack Base Creation: Difference between revisions
(Created page with "{{Item navbar |model= |about=Heater_Controller_Stack_Base |product=heater+controller+stack+base}} == Instructions == # Prepare the components #: Ensure all components are available # Mount the principal CCA heater controller 6 channel v.C #: Place the CCA heater controller 6 channel v.C on a clean, flat workspace #: Ensure the mounting holes are aligned and ready for the next step # Attach the CCA stack power boards #: Take the first CCA stack power board and align it...") |
No edit summary |
||
Line 16: | Line 16: | ||
#: Secure the CCA stack power board in place using the appropriate fasteners | #: Secure the CCA stack power board in place using the appropriate fasteners | ||
#: Repeat this process for the second CCA stack power board on the opposite side of the heater controller 6 channel v.C | #: Repeat this process for the second CCA stack power board on the opposite side of the heater controller 6 channel v.C | ||
# Install | # Install the nylon standoffs | ||
#: Locate the four corner mounting holes on the CCA heater controller 6 channel v.C | |||
#: Attach the nylon standoffs 4-40 x 1/4 hex x 1/2 to each of the four corners, ensuring they are securely fastened | |||
#: These standoffs will provide the necessary spacing and support for the assembly, ensuring proper alignment when installed into the system | |||
# Final check | |||
#: Verify that all components are securely attached and properly aligned | |||
#: Ensure that all connections between the heater controller 6 channel v.C and the CCA stack power boards are tight and functioning correctly |
Revision as of 14:13, 21 August 2024
Instructions
- Prepare the components
- Ensure all components are available
- Mount the principal CCA heater controller 6 channel v.C
- Place the CCA heater controller 6 channel v.C on a clean, flat workspace
- Ensure the mounting holes are aligned and ready for the next step
- Attach the CCA stack power boards
- Take the first CCA stack power board and align it on one side of the heater controller 6 channel v.C
- Ensure that the connectors and mounting holes are properly aligned
- Secure the CCA stack power board in place using the appropriate fasteners
- Repeat this process for the second CCA stack power board on the opposite side of the heater controller 6 channel v.C
- Install the nylon standoffs
- Locate the four corner mounting holes on the CCA heater controller 6 channel v.C
- Attach the nylon standoffs 4-40 x 1/4 hex x 1/2 to each of the four corners, ensuring they are securely fastened
- These standoffs will provide the necessary spacing and support for the assembly, ensuring proper alignment when installed into the system
- Final check
- Verify that all components are securely attached and properly aligned
- Ensure that all connections between the heater controller 6 channel v.C and the CCA stack power boards are tight and functioning correctly